top of page

Search Results

99 results found with an empty search

  • Waldron

    At Waldron, commissioning is a thoroughly mapped, step-by-step approach designed to explore the entire operating envelope of a facility and demonstrate the project’s key outcomes have been met. Because of our focused expertise in energy system engineering, we are able to remain constructively engaged throughout the process of testing, troubleshooting, and optimizing a facility’s performance.

  • New Page | Waldron

    At Waldron, commissioning is a thoroughly mapped, step-by-step approach designed to explore the entire operating envelope of a facility and demonstrate the project’s key outcomes have been met. Because of our focused expertise in energy system engineering, we are able to remain constructively engaged throughout the process of testing, troubleshooting, and optimizing a facility’s performance.

  • NATIONAL INSTITUTES OF HEALTH | Waldron

    < Back to all projects NATIONAL INSTITUTES OF HEALTH LOCATION: Bethesda, MD STUDY DATE: May 2016 – April 2017 SIZE & TECHNOLOGY: Combustion Turbine, Chilled Water Storage, Electrical Distribution System FIRM ROLE: Feasibility Study NAICS: 541330, 237130, 237120, 236220, 221112, 221117, 221118, 221121, 221122 Waldron performed a comprehensive utility study for NIH to evaluate the possibility of expanding the existing utility plant. The campus is presently served by a nominal 23 MW cogeneration facility, which is located adjacent to an existing thermal plant consisting of 60,000 tons of nameplate chilled water production capacity, with both steam and electric motor driven chilling capabilities, and five boilers with a nameplate production capacity of 800 kpph. Waldron developed a model for the entire campus utilizing existing utility data, and taking into account infrastructure upgrade projects that were planned, but not yet implemented, including an upgrade to the existing combustion turbine, a modification to the campus electrical distribution system, and the introduction of approximately 8 million gallons of chilled water storage. As part of the analysis Waldron reviewed fuel supply opportunities with local utility, identified electrical switchgear upgrades that would be required to support a new cogeneration option, and analyzed multiple sizes and types of generation to identify the optimal technology and size for additional on-site power generation. As part of the analysis, Waldron reviewed air emission constraints on generator sizing as well.

  • MONTCLAIR STATE UNIVERSITY MICROGRID | Waldron

    < Back to all projects MONTCLAIR STATE UNIVERSITY MICROGRID LOCATION: Montclair, NJ DESIGN START/COMPLETION: Spring 2011 – Spring 2012 SIZE & TECHNOLOGY: 54 MW Electric 52,000 lb/hr steam, 43,000 tons chilling / 1-Solar Taurus 60 / 1-Rentech HRSG / 1-York Model YK Electrically driven Centrifugal Chiller / 1-York Model YST Steam-driven Centrifugal Chiller SCHEDULE: In-Service 2013 FIRM ROLE: Engineer of Record The Montclair State University combined heating, cooling and power plant (CHCP) became fully operational in September 2013. The goal of the project was to provide the expanding 250-acre campus with efficient and environmentally friendly energy to meet its growing needs. The state-of-the-art facility was designed to provide 100,000 pounds/hr of 125 psig steam, 4300 tons of 42 °F chilled water and 5.4 MW of electrical power to the campus’ academic, administration and residential buildings. The project also included new steam and condensate distribution piping and chilled water supply and return distribution piping to the campus buildings. Waldron’s scope of work included full mechanical, electrical, instrumentation controls, civil, structural and architectural design and engineering services. Waldron worked closely with the project developer, DCO Energy and the University to ensure that all project programming goals were met. The specified and installed equipment is highlighted by a dual fuel, 5.4 MW (nominal) Solar Taurus 60 gas turbine-generator and a 52,000 pound/hr Rentech heat recovery steam generator which includes a natural gas-fired duct burner. Other major equipment included, two packaged auxiliary boilers, one steam turbine-driven centrifugal chiller, one electric-driven centrifugal chiller, cooling towers and medium and low voltage electrical switchgear.

  • TWA FLIGHT CENTER HOTEL ENERGY CENTER | Waldron

    < Back to all projects TWA FLIGHT CENTER HOTEL ENERGY CENTER LOCATION: New York, NY DESIGN START: Sept. 2016 DESIGN COMPLETION: Dec. 2016 IN-SERVICE: January 2019 SIZE & TECHNOLOGY: 3x335kW GE-Jenbacher, 2×280/510kW/kW-hr Energy Storage System (ESS) FIRM ROLE: Engineer, Permitting Support, Commissioning Waldron was contracted as the Engineer of Record for the energy center serving the historic TWA Flight Center Hotel at JFK Airport. MCR Development is the investment firm redeveloping the iconic landmark into a new state-of-the-art hotel. Waldron’s role is to design a grid independent combined cooling, heating and power facility for the project. The equipment will include three nominal 335kW CHP engines, with two 280/510kW/kW-hr ESS system. The design scope is a comprehensive engineering scope that will provide a fully coordinated design. The BIM model will be coordinated with and turned over to the building contractor, as well as technical documents that are ready to be issued for bidding and construction. Waldron was the commissioning agent for the project.

  • NATICK SOLDIER SYSTEMS CENTER | Waldron

    < Back to all projects NATICK SOLDIER SYSTEMS CENTER LOCATION: Natick, MA STUDY DATE: May 2017 – July 2019 FIRM ROLE: Feasibility Study NAICS: 541330, 237130, 237120, 236220, 221112, 221117, 221118, 221121, 221122 Waldron performed a study on the behalf of Constellation to evaluate the installation of a CHP plant at the NSSC campus. The basis for the study was an hourly utility model that was developed from utility load and cost information supplied by NSSC. The objective of the project was to determine the optimal-sized prime mover, evaluate the financial performance of the project, and develop a cost estimate to construct and commission the facility. Waldron also evaluated the utility modifications and interface changes required to operate the facility electrically as a Microgrid with thermal distribution loops. The recommended configuration is proceeding as a third party paid ESPC project.

  • GENERADORA ELECTRICAL DEL NORTE | Waldron

    < Back to all projects GENERADORA ELECTRICAL DEL NORTE LOCATION: Puerta Barrios, Guatemala SIZE & TECHNOLOGY: 5.8 MW Turbo Expander, Super Critical Propane, Cycle Evaporative Cooling DESIGN START: Fall 2012 IN SERVICE: Spring 2013 SCHEDULE: Construction Start Winter 2013, Construction Complete Summer 2013 FIRM ROLE: Engineering, Procurement Generadora Electrical Del Norte (Genor), a Guatemalan independent power producer, owned a 40 MW heavy fuel oil-fired reciprocating engine plant in Puerto Barrios, Guatemala. Recognizing the benefits of an improved plant heat rate, Genor under-took an analysis of ways to improve the output and efficiency of the Puerto Barrios facility. A number of options were analyzed to “combine cycle” the plant. The plant selected the Organic Rankine Cycle ORC-AT, as designed by Waldron. Waldron has an exclusive license agreement to design and construct the ORC-AT cycle. The cycle consists of a two-stage heat recovery system producing supercritical propane from exhaust waste heat. Energy in the propane is converted to shaft horsepower in a two-stage turbo expander coupled to a single generator via a common gearbox. Heat from exhausted propane is recuperated against propane prior to recycling to the superheater. Cooling for the cycle is via a bank of evaporative condensers. The plant will produce a net output of 4.0 MW for sale to the grid with the addition of no fuel input.

  • YALE UNIVERSITY ELECTRICAL WORK | Waldron

    < Back to all projects YALE UNIVERSITY ELECTRICAL WORK LOCATION: New Haven, CT PROJECT DATES: 2013 – 2016 FIRM ROLE: Designer, Commissioning Waldron has completed multiple projects for Yale University. Below are some of the electrical focused projects that have been completed. 1. Supplemental Generator Project a. Designed and installed 3 mobile generators to provide supplemental power to the Yale University Campus. The mobile generators operate in parallel with existing turbine generators and emergency generators. The three mobile generators run in parallel with each other and have load share capability. b. Controls of the generators are designed to operate the generator from three locations, local manually, chiller plant control room-automatically and the central power plant control room automatically. Controls for the new switchgear were connected into the DCS and existing synch panel for remote control. Raise/Lower voltage and frequency, synch check and other interlocks will be designed as needed. c. Arc Flash Study completed for all new equipment. d. Developed the Sequence of Operation for the generator control system. 2. New Vista Key Control Project a. Designed and commissioned the new Vista Switch Key Interlock Controls between four existing 15KV breakers. The Vista Switch Key Interlock Controls allow the associated 15 KV circuit breaker to be closed on a dead bus when the vista switch is open. This energizes the vista switch on the campus side of the switch and allows the utility to perform phase checks at the vista switch. The vista switch is not allowed to close if the key interlock switch is activated. All synchronizing remains across the 15KV breakers. b. Developed the Sequence of Operation for the Vista Switch Key Interlock control system.

  • CONSULTING | Waldron

    At Waldron, commissioning is a thoroughly mapped, step-by-step approach designed to explore the entire operating envelope of a facility and demonstrate the project’s key outcomes have been met. Because of our focused expertise in energy system engineering, we are able to remain constructively engaged throughout the process of testing, troubleshooting, and optimizing a facility’s performance. CONSULTING At Waldron, commissioning is a thoroughly mapped, step-by-step approach designed to explore the entire operating envelope of a facility and demonstrate the project’s key outcomes have been met. Because of our focused expertise in energy system engineering, we are able to remain constructively engaged throughout the process of testing, troubleshooting, and optimizing a facility’s performance. STEP-BY-STEP GUIDANCE PROJECT DEFINITION In-depth commissioning requires a thorough understanding of project goals. As with all of our services, the starting point is a detailed understanding of the specific financial, environmental and functional criteria established at the project outset. This knowledge informs the planning process. PLANNING There are three levels of planning: project level sequencing of system energization and functional testing with a facility, detailed step-by-step commissioning procedures for each system that guide the start-up and testing processes, and daily plans convened by Waldron’s commissioning manager on-site to coordinate all parties associated with or affected by the work. Much of our work is accomplished in operating facilities and requires a thorough understanding of the impacts commissioning will have on existing systems, as well as the ability to develop contingency plans. TESTING AND RESPONDING Commissioning is not a straight line from A to B: a thorough commissioning process is a daily encounter with the unexpected. Waldron’s commissioning teams excel at providing leadership and technical guidance to clients, contractors and operations teams when troubleshooting is necessary, and are capable of efficiently realigning resources to keep the process moving forward. Given the opportunity, we are not passive observers, but active contributors to the resolution of difficulties encountered. DOCUMENTATION Waldron provides daily reports of commissioning activities, as well as annotated procedures that document the step-by-step outcomes realized during the commissioning process. The result is a wealth of information for the facility owners and operators. It is possible to understand exactly what was tested, what worked and what didn’t and why, and how the deficiencies were resolved. The result is a clear roadmap for future operations.

  • HARVARD BLACKSTONE – BOILER 13 | Waldron

    < Back to all projects HARVARD BLACKSTONE – BOILER 13 DESIGN START/COMPLETION: Spring 2006 – Summer 2007 SIZE & TECHNOLOGY: 5.0 MW Electric, 150,000 lb/hr steam fired boiler / backpressure steam turbine IN-SERVICE: Fall 2008 FIRM ROLE: EPC – Engineering, Procurement Support, Construct, Commissioning In 2003, Harvard purchased the Blackstone Station from NSTAR to insure a secure source of steam to serve the future campus expansion. Waldron was retained to provide technical due diligence for the purchase. Waldron was challenged by Harvard to develop a plan for Blackstone that would meet the Campus growth needs into 2020. The first step in the plan was the installation of Boiler 13, underground fuel oil storage, a steam turbine generator and a complete upgrade to the electrical and mechanical systems. Waldron’s scope was to develop the construction plans and specifications, construction management of the project for Harvard, commission, and test the new equipment.

  • JAMAICA BROILERS | Waldron

    < Back to all projects JAMAICA BROILERS LOCATION: Spring Garden, Jamaica IN-SERVICE: 2002 SIZE & TECHNOLOGY: 15 MW Heavy Oiled Fired Reciprocating Engine FIRM ROLE: Owner’s Engineer Waldron Engineering was engaged to develop a design concept for a cogeneration plant at a food processing facility. The plant size was 15,300 KW with 50,000 lbs/hr of steam generation. The prime movers for this project are multiple #6 oil fired Wartsilla reciprocating engines exhausting into a single heat recovery steam generator, a dual fuel package boiler and a hot water absorption chiller. Waldron Engineering oversaw the letting of the EPC contract and the commissioning of the plant systems as the Owner’s Independent Engineer.

  • MIT LINCOLN LABORATORY FEASIBILITY STUDY | Waldron

    < Back to all projects MIT LINCOLN LABORATORY FEASIBILITY STUDY LOCATION: Bedford, MA PROJECT START: October 2019 PROJECT COMPLETION: April 2020 FIRM ROLE: Feasibility Study MIT Lincoln Laboratory (MITLL) is a federally funded research and development center chartered to apply advanced technology to problems of national security. MITLL occupies ~2.5 million GSF. Of that 2.5M GSF, 2.0M GSF is located on 110 acres (20 acres of which are MIT property) on the eastern perimeter of Hanscom Air Force Base. The majority of the campus buildings were constructed during the 1950s and 1960s. The last major building, Building S, was completed in 1994. MITLL is in the process of reviewing its real estate needs as well as beginning the implementation of a series of phased projects that will reshape the campus. MITLL is planning a complete revitalization of the campus which includes numerous new facilities. Waldron was retained to develop a Utility Master Plan to support both the new and existing facilities. The plan includes our hybrid approach to central plants, combining solar PV, battery energy storage system and trigeneration into a single centralized plant that will minimize utility cost, minimize greenhouse gas impacts, and provide for 100% supply of utilities in the event of a utility outage.

© 2023 Waldron Engineering & Construction, Inc. • Waldron Engineering of New York, P.C.

CA Contractor License #1126806

Westchester County HI License #WC-38167-H24

bottom of page